our building process

For those of you that have never built before, or, built several years ago, we have taken the opportunity to share with you the various stages of construction that you will witness as we construct your new home.  Depending upon the time of year, some of the exterior stages may occur out of order as compared to the following list.

Staking

staking process house staking home staking process


The Engineering company places lath on your lot representing the footprint of the house and garage.  You will see the lath at each corner of the house where two walls join.

During this time, a temporary electrical power pole is installed adjacent to the green electrical transformer at the corner of your lot.

______________________________________

Excavation

excavation process new home excavation excavating


The Excavation company digs the basement for your new home and stockpiles the dirt for later use.

______________________________________

Footings

footings process concrete foundations footings for new home


The Concrete Foundation company sets up and pours the concrete footings.  Footings are the support for the Basement and Garage walls.

______________________________________

Foundation

foundation process foundations foundation for new home construction


The Concrete Foundation company sets up and pours the foundation walls of the Basement and Garage walls.

______________________________________

Plumbing (Groundworks)

plumbing groundwork plumbing process plumbing groundwork for new homes


The Plumbing company installs the pipes that will be below the basement floor as well as connecting to the water lines at the street:  domestic water, sanitary drains and storm sewer drains. 

______________________________________

Backfill

backfill process backfill for new homes backfill during construction


After the foundation walls have sat for approximately 5-7 days, the Excavation company returns and places dirt alongside the foundation walls.  Sand is placed inside the Garage in preparation for the Garage floor and gravel is placed in the Basement in preparation for the Basement floor.

______________________________________

Concrete Flatwork

concrete flatwork process concrete flatwork for new house construction


The Concrete Flatwork company pours the concrete for the Basement floor, Garage floor and sometimes the Front Porch.

______________________________________

Framing Carpentry

framing process framing a house framing carpentry


The Framing Carpenters arrive and start constructing your new home.  Floor joists, walls, roof trusses, roof sheathing, windows and exterior doors, and siding are installed.  The rear deck may also be constructed at this time.

After the roof is completely sheathed, the Roofing contractor arrives and installs roofing felt on the sheathing to keep the interior of the house dry.

______________________________________

Roofing

roofing process roofing of a new house


After the siding has been applied, the Roofing company installs the shingles on the roof.

______________________________________

Mechanicals (Rough-In)

mechanical rough in mechanical rough in process mechanics to a house


The Heating and Cooling, Plumbing, Electrical, Central Vac, and Security companies install the heating and cooling, plumbing, electrical, central vac, and security components that will be inside the walls.  The fireplace,  furnace and air conditioner are also installed at this time.

______________________________________

Concrete Flatwork

concrete flatwork concrete process for new home construction concrete flatwork


The Concrete Flatwork company returns and pours the concrete for the driveway, sidewalk from the driveway to the Front Porch as well as the rear patio and city sidewalks.

______________________________________

Masonry

masonry process


The Stone Masons apply cultured stone to the exterior façade. 

______________________________________

Painting

exterior paint exterior painting process painting the exterior


The Painting company paints the exterior of the house.  This may sometimes occur later in the process when the interior of the house is painted.

______________________________________

Insulation

insulation insulation process insulation process for new home construction


The Insulation company installs the insulation and insulation products in the house and Garage. After the sheetrock has been installed, the Insulation company will return to insulate the attics of the house and garage as well as install insulation blankets on the basement walls. 

______________________________________

Sheetrock

sheetrock sheetrock process sheetrock process for new home construction


The Drywall company installs the sheetrock on the ceilings and walls of the House and Garage.  Drywall compound is applied to the nails and screws as well as the seams.  Texture is then applied to the ceilings and walls of the House and Garage.

______________________________________

Garage Doors

garage doors garage doors garage


The Garage Door Company installs the Garage Doors and returns later to install the openers and keypad.

______________________________________

Hardwood Floor

hardwood flooring hardwood flooring process installing hardwood


If the Hardwood flooring is job-finished, it is installed at this time.

______________________________________

Trim Carpentry (Partial)

trim carpentry trim carpentry trim carpentry


The Trim Carpenters install the cabinetry, interior doors, baseboard, casing, crown molding, stair treads and stair railings, as well as any built-ins or custom trim details.

______________________________________

Paint

paint stain paint stain paint stain process


The Painting company applies stain/paint to all of the woodwork.  Next, the ceilings are painted with the walls of the House and Garage competed last.

______________________________________

Masonry

fireplace brick fireplace masonry masonry process


The Stone Masons install cultured stone on the interior of the house, typically on the fireplace.

______________________________________

Gutters
The Gutter company installs the gutters and downspouts.

______________________________________

Countertops

countertop


The countertops are installed in the Kitchen, Bathrooms and Laundry Room.

______________________________________

Mechanicals (Partial Trim Out)
The permanent thermostat is installed, light fixtures, outlets and light switches are installed, permanent electric and gas is connected to the house from their respective locations.

______________________________________

Floor Coverings

floor coverings floor coverings process tile process


Tile is installed in the Bathrooms on the floors as well as the Master Bathroom shower when applicable.
Carpet is installed next in the selected rooms.
The Hardwood floor is sanded and finished if Job-finished, otherwise it is installed at this time.

Shelving

shelving


Shelving is installed in all closets.

Mechanicals (Completed Trim Out)

mechanics completed mechanics complete mechanics


Plumbing fixtures are installed in the Kitchen and Bathrooms.

Appliances are installed.

Central Vac ports, vac pan and the primary unit are installed.
 
The fireplace is set up and turned on.

Mirrors/Shower Doors

mirrors and doors shower doors mirrors


Mirrors are installed in the Bathrooms as well as shower doors if applicable.

Trim Carpentry (Completion)
The Trim Carpenters return and install base shoe (quarter round wood trim) in all of the hard-surface rooms.  Door and Bathroom hardware are also installed at this time.

Grade/Sod

grading process sodding sod


The Landscaping company performs a final grading of the lot and installs the sod.  If an irrigation system or landscaping have been selected, these are installed at this time as well.

Cleaning

cleaning


The Cleaning company washes all of the windows and exterior doors as well as a thorough clean of the House and Garage

Walk-Through

walk-through walk through process final phase


A walk-through is performed to familiarize you with how your house “works,” tips for the maintenance of your new home, as well as the compilation of a list of any items that need to be addressed.